a class project can be completed by 2 people in 36 days in order for it to be complete in 9 days how many other people must participate?
Answer provided by our tutors
Let 'x' represent the number of people needed to complete the project in 9 days.
The number of people for the project is inversely proportional to the number of days needed to complete, that is:
2*36 = x*9
........
click here to see the equation solved for x
........
x = 8 people
8 people must participate to finish the project in 9 days.