It takes 24 workers to complete the job in 5 days. How many days would 15 workers take to do the same job, assuming all the workers work at the same pace?
Answer provided by our tutors
Let 'x' represent the number of days that 15 workers need to finish the job.
24/15 = x/5
x = 24*5/15
x = 8 days
15 workers will need 8 days to do the same job.