Twelve man finish the job in 16 days five men were working at the start and after 8 days 3 more were added. How many days will it take to finish the job?
Answer provided by our tutors
Twelve man finish the job in 16 days five men were working at the start and after 8 days 3 more were added. How many days will it take to finish the job?
Solution:
it takes x days to finish the job
(5*8)/(12*16)+(8*(x-8))/(12*16)=1
x=27
So it takes 27 days to finish the job