Problema Solution
if it takes 4 men and 3 hours to pave a playground, how many hours will it take 12 men to complete the same task?
Answer provided by our tutors
It takes 4 men and 3 hours to pave a playground.
More men will finish the playground faster - less time (inverse proportion)
If we have 3 times more men that is 4*3=12 men the playground will be finished 3 times faster then before, that is, in 3 / 3 = 1 hour.
Or we can write this down like this:
4 : 12 = x : 3 (inverse proportion)
12 * x = 4 * 3
12* x = 12
x = 1 hour
12 men will complete the task in 1 hour time.