24 men can complete a work in 16 days.32 women can complete the same work in 24 days.16 men and 16 women started working and worked for 12 days.how many more men are to be added to complete the remaining work in 2 days?

Answer provided by our tutors

24 men can complete a work in 16 days, thus one man's work progress each day = 1/(16*24)

women can complete the same work in 24 days, thus one woman's work pregress each day = 1/(24*32),

16 men and 16 women started working and worked for 12 days, their progress now = 16*12*1/(16*24) + 16*12*1/(24*32) = 1/2 + 1/4 = 3/4,

now they need to finish the rest of work 1-3/4=1/4 in 2 days,

thus the number of men = 1/4 / [1/(16*24)] = 96 men.