If 3 street sweepers can finish a certain job in 1 hr and 15 min, how long will it
take 5 sweepers to finish the job?
Answer provided by our tutors
If 3 street sweepers can finish a certain job in 1 hr and 15 min, how long will it take 5 sweepers to finish the job?
5 sweepers will do in less time.
time required by 5 sweepers =3/5*1hr.15min.
convert time into min =60+15=75min.
=0.6*75min.
=45 min.