a carpenter worked alone for 1 day on a job that would take him 6 more days to finish. He and another carpenter completed the job in 4 more days. How many days would it have taken the second carpenter to do the complete job working alone?
Answer provided by our tutors
A carpenter worked only 1 day on something that takes him 6 MORE days.
Means;
Carpenter finishes his work in 7 days.
Let his buddy finish the same task in x days.
Respective rates per day:
1/7 AND 1/x
To complete 1 work:
First guy worked for 5 days @ rate=1/7 per day.
Second one worked for 4 days @ rate=1/x per day
Expression:
Days*Rate=Work
5*1/7+4*1/x=1
5x+28=7x
2x=28
x=14 days.