I need to collect 119,822 documents. Assume that it will take ten minutes per document. If I need to accomplish this work in twenty business days, and I use people who work eight hours per day, how many people will I need to complete the task on time?

Answer provided by our tutors

the total time to collect 119,822 documents is


119,822*10 = 1198220 min = 1198220/60 hr = 59911/3 hr = 19970 hr 20 min


one worker in 20 business days will work 20*8 =160 work hours


(59911/3)/160 = 124.81 and since the number of people is integer follows


I will need 125 people to complete the task on time.