Problema Solution

If 4 workers can finish a project in 9 hours, how long would it have taken for 3 workers?

Answer provided by our tutors

let


x = the number of hours that 1 worker needs to finish the project alone


1/x = the rate of 1 worker per hour


4 workers can finish a project in 9 hours:


4(1/x) = 1/9


by solving we find:


x = 36 hr


click here to see the step by step solution of the equation:


Click to see all the steps



3 workers will take 3 times shorter time than 1 worker or:


(1/3)*(36) = 12 hr


it will take 12 hours for 3 workers to finish a project.